Tagged: alltel arena

6-Inch Error in Laying Concrete Puts Alltel Arena Project Behind Schedule

by David Smith 3/31/2014 12:00 am

Construction on Alltel Arena is more than a month behind schedule because of an error in geometric calculations by the concrete contractor, the senior project manager for the $53 million construction job says.

Here's Why March Madness Hasn't Returned to Verizon Arena

by Arkansas Business Staff 4/1/2013 12:00 am

It’s unclear if any NCAA Men’s Division I Basketball Tournament games will ever return to North Little Rock. UALR still lobbies, but there's one factor in the way.